In and Out on Time: Navy Tackles Maintenance Backlog With New Initiatives in Contracting and at Shipyards

Rear Adm. Stephen Evans (left), commander of Carrier Strike Group 2, and Rear Adm. Sara A. Joyner tour the dry dock of the aircraft carrier USS George H.W. Bush in Norfolk Naval Shipyard during the ship’s incremental availability maintenance period. U.S. Navy/Mass Communication Specialist Seaman Stuart A. Posada

The U.S. Navy is taking some new initiatives
to sustain the ships of its busy fleet, including additional oversight, new
contracting strategies, shipyard workload stability and capital investment in
shipyard infrastructure.

The initiatives are focused on getting ships and submarines through their maintenance periods on time and back to the fleet to meet the requirements of combatant commanders. As the fleet — run hard by decades of war or crisis — grows in numbers, the challenge becomes greater.

Check out the digital edition of November’s Seapower magazine here. 

In an Aug. 23 release, James
Geurts, assistant secretary of the Navy for research, development and acquisition,
announced that the Department of the Navy was establishing a new deputy
assistant secretary of the Navy for sustainment (DASN-S) to develop, monitor
and, implement policy and guidance throughout the Navy who “will enable us to
better plan, program, budget and execute the Navy’s sustainment mission.” 

“Sustainment
is as critical as new construction to ensure the Navy is ready to deploy,”
Geurts added. “This position will allow us to improve and align the complex
drivers of maintenance and modernization completion — that in turn will
increase our output to the fleet. We have to get better, and this will help.” 

“We have grown the size of the naval shipyards from 33,850 [workers] to over 36,100 in the past three years. The goal was to get to 36,100 by the start of [fiscal 2020]; we actually got there a year early. That is good news, and that capacity is starting to yield some results to deliver the last eight of the last nine carriers [from maintenance] on time.”

Vice Adm. Thomas Moore, Naval Sea Systems Command

The
new DASN-S will have funding oversight and will “manage Navy and Marine Corps
sustainment and life-cycle management policies,” the release said. The new
position was authorized by Congress in the 2018 National Defense Authorization
Act. 

The new deputy “will help facilitate and
ensure we are putting the same level of aggressiveness into new tools, new ways
of doing business, new ways to contract for that effort, making sure that
they’ve got the full horsepower of the secretariat as [Naval Sea Systems
Command Vice] Adm. [Thomas] Moore’s teams execute that effort,” Geurts said in
an Aug. 23 media roundtable at the Pentagon, which Moore also attended.  

Moore said at the event that the Navy had been
focusing on building the workforce at its shipyards — necessary because the
backlog of ship maintenance occurred in part due to a shortage of skilled
workers.

The Freedom-class littoral combat ship USS Detroit receives scheduled maintenance and upkeep during dry-dock maintenance at BAE Systems shipyard in Jacksonville, Florida, in March 29. U.S. Navy/Mass Communication Specialist 3rd Class Nathan T. Beard

“We have grown the size of the naval shipyards
from 33,850 [workers] to over 36,100 in the past three years,” he said. “The
goal was to get to 36,100 by the start of [fiscal 2020]; we actually got there a year early. That is good news,
and that capacity is starting to yield some results to deliver the last eight
of the last nine carriers [from maintenance] on time.” 

Moore said the Navy also is focused on getting
workers qualified more quickly by establishing learning centers. 

“Right now, what we are seeing is that [for]
the average worker — from the time we bring them in the door to the time they
are a productive person — we have cut the time in about half. … Even though
half my workforce has less than five years of experience, that trend is also
starting to turn in the right direction.” 

Moore also said the 20-year Shipyard
Infrastructure Optimization Plan (SIOP), implemented in March 2018 for aircraft
carriers and submarines in Navy-owned shipyards, has already “resulted in
significant investments in capital expenditures, great support from the Navy
and the budgets in ’18, ’19 and ’20 and great support from [Congress]. That is
a key enabler.” 

He pointed out that many shipyards are
hundreds of years old and the SIOP is engaged in building them into 21st
century naval facilities by modernizing dry docks, replacing outmoded equipment
and improving workflow. In the 2021 budget proposal, the Navy plans to include an initiative
like SIOP to come up with creative ways to make capital investments in private shipyards.   

Links of the anchor chain of the aircraft carrier USS George H.W. Bush lay on a barge next to the carrier in Norfolk Naval Shipyard during the ship’s planned incremental availability maintenance period. U.S. Navy/Mass Communication Specialist Seaman Michael Joseph Flesch

“We will look at dry-dock capacity, capital
expenditures, etc.,” Moore said. “It’s a little bit different to execute the
plan because, unlike in the public sector where we own everything and we can
budget for this, this [involves] individual private companies, and so, we’re
working with [Geurts] to come up with some creative ways as to how we could go
execute this. For instance, we could do like we do with small business
innovative research. The Navy would have a pool of money and, if industry came
to us with a good idea in their yard, maybe we could self-fund some of
it.”  

Geurts said that the Navy is looking at other
shipyards that could be certified for Navy work, even though they have no
current Navy contracts.  

The
Navy is also executing a Perform to Plan initiative that identifies performance
gaps and barriers to execution so they can be addressed to improve performance,
according to the Aug. 23 release. 

USS Boise Illustrates Submarine Upkeep Challenges

Moore spoke of submarine maintenance being the
toughest challenge, noting that the extensive delay in returning the Los
Angeles-class attack submarine USS Boise to service was “the poster child” of
that challenge. The Boise completed its last deployment in 2015 and lost its
dive certification in 2017. He said the Boise delay caused the Navy to
recognize that the sea service did not have enough shipyard capacity for its submarines.  

There are only two private shipyards capable
of handling work on nuclear-powered submarines: Huntington Ingalls Industries’ Newport
News Shipbuilding in Virginia and General Dynamics Electric Boat in
Connecticut. These companies are occupied with construction of new submarines.  

The Los Angeles-class attack submarine USS Boise arrives in June 2018 at Huntington Ingalls Industries’ Newport News Shipbuilding division to begin its extended engineering overhaul. Huntington Ingalls Industries/Ashley Cowan

“We were kidding ourselves that we could get
the work done,” Moore said. “In many ways, Boise caused us to really take a
hard look at what we needed to do in the naval shipyards and, also, caused us
to recognize that we would like to have some surge capacity in the private
sector, working with both Newport News and [Electric Boat] to give them work
when it makes sense. We have had some challenges with them the first time for
them to do submarine maintenance work in a long time. It is different than
building submarines. And so, they have had some proficiency challenges, which
we are working our way through.  

“We have to be careful that we’re not stepping
into the new construction lane with everything going on with Columbia [ballistic-missile
submarine] and [Virginia-class attack submarine] Block V, etc.,” he said.
“Newport News has expressed a very strong interest in developing a capacity to
do submarine sustainment over the long haul similar to what they do with carrier
maintenance today.” 

“In many ways, Boise caused us to really take a hard look at what we needed to do in the naval shipyards and, also, caused us to recognize that we would like to have some surge capacity in the private sector.”

VICE ADM. THOMAS MOORE

Moore said the Boise “will actually start at
Newport News probably in April 2020.” 

He explained that delays can be described in
terms of maintenance delay and idle time, the latter being the time a submarine
is idle awaiting the beginning of maintenance. Some idle time results when the
Navy squeezes more operational time out of a sub deployment, causing a boat to
miss its slot in the maintenance schedule. 

“What the data told us is that, if you
consider the variables to be idle time and maintenance delays, 80% of that was
due to the maintenance delays, and only about 20 percent of it was idle time,”
Moore said. “What we have focused on first from a systems standpoint is to fix
the maintenance delays and that is by growing the capacity of the shipyard.
We’re starting to see those maintenance delays [were cut] in half between ’18
and ’19 [and] the amount of workload carryover between what we saw at its peak
in ’16 to today has been reduced by 75%.” 

The idle time is coming down as well because
of the Navy’s initiatives — “down to about 1,800 total days of idle time, of
which 1,200 is Boise,” Moore said. “When you take Boise off the table, it’s
really relatively small and my expectation is that, by the end of fiscal ’20,
we will have no more idle time.”  

For the Surface Fleet, Enticing Private Yards to
Build Capacity
 

In the private shipyards, where much surface
ship maintenance takes place, the Navy is working to entice growth in capacity.
Results so far are positive. 

“The data is getting better,” Moore said.
“Last year, we delivered 16% of our DDGs [guided-missile destroyers] on time.
“This year, it was up to about 40%, and we are forecasting that the next eight
DDGs will be on time.”

“Currently, 75% of the DDGs are on plan to
their life-cycle health assessment and, by 2023, we will have gotten the other
25% back on plan,” he added. “The [nuclear power community] have always been
very meticulous about staying onto the class maintenance plan. We’ve been a
little bit less rigorous on the surface side of the house probably over the
last 10 to 15 years, and we’ve paid the price for that.”  

The starboard anchor aboard the aircraft carrier USS George H.W. Bush is lowered into a dry dock for maintenance. U.S. Navy/Mass Communication Specialist Seaman Steven Edgar

Moore said that part of the success is
attributed to a new contracting strategy: “bundling [shipyard] availabilities
together so that they have an opportunity to project workload out,” enabling
shipyards to see the stability of enough work to cut costs and maintain the  workforce.

He said the Navy was not happy with the cost
and schedule performance of cost-plus contracts with a single company for five
years at a time. The service then switched to fixed-price contracts for one ship at a time, but
this made the private shipyards reluctant to hire additional workers when they
did not know if they would win the next contract. With the shipyard reluctant, hiring lagged behind the workload, resulting in delays in
delivery back to the fleet. Bundling fixed-price contracts is the new plan. 

Moore has been working with Geurts on bundling
availabilities together so that if a shipyard wins, it is “going to win
availabilities over a two-, three-, four-year period head-to-toe, then you’ve
got a stable plan and you can then go make capital investments in your plan,
and you can hire to have that workforce trained.”  

“My priority for the fleet is, ships come in on time, ships go out on time and they go out with all the work done.”

James Geurts, assistant secretary of the Navy for research, development and acquisition

Another factor in delayed delivery is having maintenance
plans that aren’t executable. Moore said that working with the fleets to
provide an executable, level-loaded plan for the shipyards, staying away from
overloading them, is yielding progress in tackling the workload.  

Moore
said that NAVSEA’s “partnership with the fleets has been as good as it has ever been in
the 25 years [that] I’ve been a maintenance provider.” 

The Navy also is reducing quality assurance
checkpoints by 50%, which will cut shipyards’ costs. Moore cited the example of
a DDG hull being painted at a Vigor shipyard adjacent to a commercial ferry also getting fresh
paint. Vigor’s president pointed out to Moore that painting the DDG cost four
times more and took twice as long as the ferry work — and the difference was the
Navy’s onerous checkpoints. The ferry’s painter also provided a warranty. Moore
said the Navy will conduct a pilot project this year with two ships under a
contract with a warranty. 

“In return, we’ll reduce the checkpoints, and
let’s see if we can get the cost and the schedule down,” Moore said. “There are
a number of things out there like that that, over years, we have just added
bureaucracy into the system that really doesn’t add any value to get the work
done.” 

Geurts, referring to the Navy’s 30-year
maintenance and modernization plan that supplements the 30-year shipbuilding
plan, said: “We’ve got to get those balanced up right so that we cannot only
deliver the capabilities needed but sustain them to provide the operational
commanders the capabilities they need.  

“My priority for the fleet is, ships come in
on time, ships go out on time and they go out with all the work done,” he said.
“The fleet uses the term ‘on time in full.’ So, my priority is getting
credibility in the system so that a fleet commander is confident when they turn
a ship over to us to go do the maintenance work that it comes out on time and
in full. 

“Part of the rigging for speed is not just
delivering in peacetime, it’s really getting prepared for wartime,” he said.
“Ready to me means ready tonight to fight and then ready for the fights that
are coming in the future. It’s not just about meeting a schedule or a budget
target. If we can’t do the peacetime stuff well with credibility, we’re really
going to struggle in wartime mode.” 

Geurts said that sustaining the lethality of the
fleet is a matter of maximizing availability, capacity and capacity, and “the
trick is getting those synchronized and mutually supporting, not competing. To
some degree, if you spend too much time worrying about new construction but you
don’t worry about maintenance, then you’re not maximizing that investment. If
all you are doing is worrying about maintenance and not tracking the costs and
trying to drive that cost down, you won’t have money to modernize and build new
things.”